Scale a plant without scaling every dollar
A plant twice as large need not cost twice as much. Shared infrastructure can produce economies of scale, but the model is valid only within a comparable range.
Cost rises less than proportionally with capacity: economies of scale in this range.
Use comparable technologies and price dates before scaling.
Cash-flow dates and signs are part of the answer. Model values retain precision; displays round money to cents. Illustrative assumptions exclude taxes and inflation unless stated.
What the model means
The power model C=aKᵇ becomes log C=log a+b log K. Two comparable points give b=log(C₂/C₁)/log(K₂/K₁); then a=C₁/K₁ᵇ. If 0<b<1, total cost rises while average cost per unit capacity falls.
Build the calculation
Power sizing changes capacity; a cost index changes price date: C_new=C_old(index_new/index_old). If both date and size change, apply both adjustments consistently. Do not automatically use a memorized exponent for a different process or capacity range.
Set up. Calculate. Explain.
Rebuild the starting scenario
Known plant cost: 400000 $; New capacity / old capacity: 2 ratio; Capacity exponent: 0.6 dimensionless. Calculate the estimated new plant cost.
Setup hint
Use comparable technologies and price dates before scaling.
Open the visual solution
- Use comparable technologies and price dates before scaling.
- Capacity ratio = 2; exponent = 0.6.
- Multiply the known cost by ratioᵇ. A cost index adjusts date; the exponent adjusts size.
Cost rises less than proportionally with capacity: economies of scale in this range.
Use comparable technologies and price dates before scaling.
Cash-flow dates and signs are part of the answer. Model values retain precision; displays round money to cents. Illustrative assumptions exclude taxes and inflation unless stated.
Checks allow 0.1% numerical rounding (minimum $0.05 or 0.001 in the stated nonmonetary unit). Interpolated factors and rates are approximations; keep table precision consistent.
Transfer the idea to a new scenario
A known plant costs $600,000. Estimate a plant with 2.5 times capacity using b=0.65.
Setup hint
Use comparable technologies and price dates before scaling.
Open the visual solution
- Use comparable technologies and price dates before scaling.
- Capacity ratio = 2.5; exponent = 0.65.
- Multiply the known cost by ratioᵇ. A cost index adjusts date; the exponent adjusts size.
Cost rises less than proportionally with capacity: economies of scale in this range.
Use comparable technologies and price dates before scaling.
Cash-flow dates and signs are part of the answer. Model values retain precision; displays round money to cents. Illustrative assumptions exclude taxes and inflation unless stated.
Checks allow 0.1% numerical rounding (minimum $0.05 or 0.001 in the stated nonmonetary unit). Interpolated factors and rates are approximations; keep table precision consistent.
For 0<b<1 and increasing capacity, what happens?
Can you defend your setup?
Can you place each amount on the timeline, match the interest period, calculate the equivalent quantity, and state the decision or limitation?